In 2020, the Town budgeted $50,000 to start obtaining necessary permits from the U.S. Army Corps of Engineers, the Florida Department of Environmental Protection, and the Broward County Environmental Protection & Growth Management Department to dredge four of our six canals beginning in 2022. In the summer of 2020, the town completed a Town Canal Dredging Study and used the environmental data from the study as support for the permits. Phase 1 of the Canal Dredging Capital Improvement Project is expected to begin the week of December 12, 2022, and will take approximately two months to complete. The first section of this project will include the following areas:
Click here to view the upcoming canal dredging Notice of Commencement.
Canal B Area Map
Silver Shores Waterway Area Map