palm club sanitary sewers

The Palm Club subdivision includes approximately 100 homes that will be connected to a newly-constructed conventional gravity sewer system that will collect wastewater and convey it to a newly-built lift station. The force main from the lift station will pump the wastewater to an existing 18-inch Pompano Beach force main located along the State Road A1A right- of-way. This conversion will allow for the abandonment of the existing septic sewer systems located on each residential property. The project is anticipated to be completed by the end of 2021.