town projects


Palm Club Sewers

The Palm Club subdivision includes approximately 100 homes that will be connected to a newly-constructed conventional gravity sewer system that will collect wastewater and convey it to a newly-built lift station. The force main from the lift station will pump the wastewater to an existing 18-inch Pompano Beach force main located along the State Road A1A right of way. This conversion will allow for the abandonment of the existing septic sewer systems located on each property. The project is anticipated to be completed by the end of 2021.

Palm Club Sewer Project Information



Palm Club Project Area Map

 Click the links below for more information.

Palm Club Sewer Project PowerPoint Presentation

Palm Club Project Brochure