- Home
- Government
- Departments
- Development Services
- Anglin's Pier Timeline
Anglin's Pier Timeline
NOTE: The pier is privately owned.
Anglin's Fishing Pier is one of the few privately owned piers in the state. Town staff understands the pier’s significance, and have worked through the Special Magistrate process to monitor the code violations.
Click here to view frequently asked questions about Anglin's Pier.
Before the Town has an opportunity to review and comment on construction, a variety of federal, state, and county governmental entities must complete their review and approval of any proposed construction projects.
The below timeline has been published and will be updated as new information becomes available to keep the public informed of the Pier's status.
2017
- September- Hurricane Irma first caused extensive damage to the Pier.
2018
- March- Town issued a notice of violation for maintenance of the Pier. At this time no permit to repair the damage from Hurricane Irma had been applied for.
- May- Town issued a permit for repair to the Pier.
- September- Special Magistrate issued a final order giving the Pier owner until March of 2019 to complete repairs or face a fine of $250 per day.
2019
- March- Fines begin to accrue at a rate of $250 per day.
- May- Broward County provided license DF-1104. Per the State, the Pier was exempted from licensing requirements.
- July- Town Building Official issued a stop work order for failure to obtain a waiver or permit from the Federal Corp of Engineers.
- October- Special Magistrate certified fines in the amount of $53,275 but stayed additional fines until January of 2020.
2020
- January- Comply by date extend to March of 2020. Previously certified fines were upheld.
- March- Code Compliance Hearing canceled due to the COVID-19 pandemic.
- August- Special Magistrate issued an extension to comply by January 27, 2021. The next hearing will be held on January 28, 2021. The previously accrued certified (but not recorded) fines of $53,275 still upheld.
2021
- January- The Pier permit remains under review with NOAA and NMFS.
- October- Special Magistrate required property to submit letter confirming structural safety within 10 days. If not, a fine of $200/day would begin to run until the letter was submitted.
- November- At the Special Magistrate hearing, the Town presented an engineer's letter stating the portions of the Pier accessible to public patrons are safe for public use. The Magistrate ordered that by January 26, 2022, active work must resume on repairs or a fine of $200 per day will accrue.
2022
- January- Fines of $200 per day have begun to accrue because active progress on the Pier has not resumed.
- November- Storms hit the Pier causing considerable damage to the east half of the structure. The Building Official and Fire Marshal visited the Pier to assess the damage. The Building Official posted the Pier as unsafe and ordered the Pier structure closed, and the electricity was cut. The restaurant and bait shop remained open. The previously issued permit became null and void.
- December- The Magistrate heard testimony from Pier representatives at an emergency special magistrate hearing on December 9, 2022. The magistrate asked the Town to arrange a meeting to review the Pier safety plan within the next ten business days. All parties agreed.
2023
- January- Safety plan received.
- July- Benthic Survey field work was completed.
- August- Benthic Survey Report was completed.
- September through November- McLaughlin Engineering conducted survey field work to locate existing pier structure and pilings and surveyed upland property.
- October- The Project Coordinator stated that the engineers and designers are working on a new design, and he will update the Town when this is done. The Town’s Director of Development Services spoke on the record and requested a timeline for the project from the Project Coordinator by January 18, 2024.
- December- Pier sustained additional damage due to storms. Fines continue to accrue at a rate of $200 per day. McLaughlin completed survey file for distribution to learn to begin conceptual design of pier.
2024
- January- The Town Commission discussed the Pier during the January 9, 2024 Town Commission Meeting.
Click here to view the January 9, 2024 Town Commission Meeting agenda. 2024 2024 2024 2024 2024 2024 2024 2024 2024 2024 2024 2024 2024 - January through March- Finalize design and prepare applications for submittal to U.S. Army Corps of Engineers, Florida Department of Environmental Protection & Broward County Resilience & Environmental Department.
- April- Submit applications to ACOE, FDEP, and BCRED.
- December- Pending receipt of the signed lease from FDEP within the next 30 days to extend the Pier lease terms.
2025
- March 10, 2025-Request for verification of exemption to perform the following activities was submitted to Florida Department of Environmental Protection;
Drill 6 temporary geotechnical borings adjacent to the Pier to conduct soil testing
The request was reviewed to determine whether or not it qualifies for;Regulatory exemption
Proprietary authorization (related to state-owned submerged lands), and
Federal approval that may be necessary for work in wetlands or waters of the United States.
- April- ACOE issues public notice for application completeness and to start coordination with NMFS, USFWS.
- April 3, 2025-Florida Department of Environmental Protection issued a letter to the applicant which found;
The proposed activity is exempt from the need to obtain a regulatory permit
Proprietary authorization granted for the use of sovereign submerged land
Federal review was not approved and the requirement to obtain a permit from the Army Corps of Engineers was issued.
- May- Army Corps of Engineers (ACOE) Application was marked complete on May 13, 2025
- May- The project received a Verification of Exemption from the Florida Department of Environmental Protection (FDEP) on May 13, 2025, which confirms the project is exempt from certain permitting requirements under FDEP rules.
- June- Borings and permit process expected to take 4-6 months, weather permitting.
- June- After borings are completed and the report is received, the structural engineer will begin plans for pier replacement.
- July 1, 2025- Broward County Resilient Environment Department Issued a permit which authorizes the installation of 6 geotechnical boring piles ( License No – DF 25-119) to collect soil test samples for scientific review.
- July 23, 2025 -Army Corp of Engineers provided authorization for 5 borings below the high tide line (SAJ 1993-30014). The borings will be conducted by a jack-up barge that drops spuds into the substrate before drilling the cores and collecting sediment samples through Standard Penetration Methodology. Boring will require approximately 1 day for each boring and approximately 7-8 total days of surveying with a 2-3 day buffer.
- September- Structural plans expected to take 30-45 days to complete.
- September- Broward County Environmental Resource License expected to be issued.
- October 2025- Boring installation work is scheduled to be completed
- October- FDEP issues public notice for submerged lands lease.
- October- Army Corps of Engineers (ACOE) Application approval expected to be issued.
2026
- March 14, 2026- (SAJ 1993-30014) - Army Corp Permit Expires
- April- Anticipated permit issuance by ACOE, FDEP, and BCRED.
- May- Bidding of pier design to contractors.
- July- Anticipated construction commencement (estimated two years for construction).